DAMOCLES
- EVG1-CT-1999-00007
START-UP MEETING
UNIVERSITY
OF MILAN
DEPARTMENT
OF EART SCIENCES
Milano
4-5
April 2000
MINUTES
PRESENT
James
Bathurst (Coordinator) (Newcastle)
Giovanni
Crosta (Milan-Bicocca)
Federico
Agliardi (Milan-Bicocca) (part of meeting)
Paolo
Frattini (Milan-Bicocca) (part of meeting)
Fausto
Guzzetti (CNR-IRPI Perugia)
Alberto
Cararra (Bologna) (Technical discussions only)
Mario
Lenzi (Padova)
Jose-Maria
Garcia-Ruiz (CSIC IPE Zaragoza)
Carlos
Marti (CSIC IPE Zaragoza)
Santiago
Rios (ITGE Zaragoza)
1
- TABLED DOCUMENTS
a)
EC Contract and Annexes I (work description), II and III
b)
Preliminary version of Consortium Agreement for Principal Contractors
2
- AGENDA
Tuesday
4 April
9.30-9.50
Welcome (Giovanni Crosta & James Bathurst)
9.50-10.10
Project Overview (James Bathurst)
10.10-13.10
Description of Individual Work Packages
10.10-10.40
WP1 CSIC/ITGE Zaragoza (Carlos Marti & Santiago Rios)
10.40-11.10
WP2 U Milan-Bicocca (Giovanni Crosta & Fausto Guzzetti)
11.40-12.10
WP3 U Padova (Mario Lenzi)
12.10-12.40
WP4 U Newcastle (James Bathurst)
12.40-13.10
WP5 U Newcastle (James Bathurst & Fausto Guzzetti)
14.30-17.30
Discussion of Work Package Links
14.30-15.00
WP1 inputs to WP3 and WP4
15.00-16.00
WP3 and WP4 inputs to WP2
16.30-17.00
WP1, WP2, WP3, WP4 inputs to WP5
17.00-17.30
Integration of end-users into the project
Wednesday
5 April
9.00-11.00
Contractual Matters
-
EC contract/requirements
-
Consortium Agreement
-
Payments
-
Technology Implementation Plan (TIP)
-
Quality Assurance
-
Publications
-
6-month report
-
Date of next meetings
-
Formal end of start-up meeting
3
- MAIN ACTIONS
-
Check
the consortium agreement and send comments to the coordinato by 31
May.
-
Bullet-point
progress reports are to be circulated by email a 2-month intervals.
The first should be circulated by Friday 2 June.
-
The
partners developing or using models should circulate a list of
the model requirements,
including the desired quality of the data and how the
data should be collected. The partners collecting data should take
these requirements
into account.
-
All
partners to send details to Fausto Guzzetti for the web site.
Fausto
will circulate requirements but these will include:
-
web
addresses of the partner institutions for linking with the
DAMOCLES web
site
-
one-page
descriptions of the study areas
-
one-page
descriptions of the models
-
information
on the DAMOCLES project from the proposal and final contract
document (to be sent by James Bathurst)
-
minutes
of the progress meetings.
-
All
partners to prepare work timetables for the first 12 months of
the project (showing
actions, deliverables, etc against month dates). The timetables
should be brought to Nice or otherwise circulated by 2 May.
-
James
Bathurst, Giovanni Crosta and Mario Lenzi to develop a flow
chart showing
how their models are linked.
-
The
next progress meeting will be in Zaragoza on 25, 26 and 27
October. Full
progress reports should be circulated two weeks earlier.
4
- WELCOME
James
Bathurst welcomed the participants to the meeting. He thanked the
partners for their
contributions to the successful proposal and stressed that
the DAMOCLES project would be a team effort. He also thanked Giovanni
Crosta for making
the necessary arrangements for the meeting to take place
in Milan.
5
- OVERVIEW
James
gave an overview of the project based on the proposal and contract
documents. The start
date was 1 March 2000 and the finish date will therefore
be 28 February 2003. The project is composed of five workpackages
but just as important are the links and exchanges between them:
the project should therefore be greater than the sum of its parts.
James emphasized
that, in addition to completing the research tasks of particular
interest to each partner, the project must provide its specified
deliverables and should deliver an overall product that meets EU
needs.
6
- DESCRIPTION OF INDIVIDUAL WORKPACKAGES
6.1
- WP1 CSIC IPE/ITGE ZARAGOZA
Jose-Maria
Garcia-Ruiz reviewed the IPE contribution. He also described
the principal field
area, which is the Pyrenees north of Zaragoza, and presented
a number of geomorphological, maximum daily rainfall and other
maps. These should
eventually go on the project web site. The field area contains
two small experimental catchments which can be used to relate
debris flow occurrence
to sediment yield. There are also some reservoirs which
have been surveyed for sediment yield data. Rainfall with a thirty-year
return period is required to trigger abundant debris flows, although
lesser rainfall can still trigger flows. It was established in
discussion that
debris flow characteristics are similar between the Alps and
the Pyrenees. The difficulty of carrying out statistical analysis with
limited data on
debris flow occurrence was noted. (A general meeting theme was
of the need to account for uncertainty in data analysis and model
output.) It was
suggested that EU policies have led to increased debris flow
occurrence. This link may therefore be a important project research
topic. Santiago
Rios indicated that ITGE was interested in the Ebro valley and
described
the project field area, to the east of IPE's area. ITGE will
support
IPE's work with information on debris flow deposits.
DAMOCLES
has two field areas in the Pyrenees, containing three principal
basins.
6.2
- WP2 UNIVERSITY OF MILAN-BICOCCA
Giovanni
Crosta, speaking also for Fausto Guzzetti and Alberto Cararra,
described the workpackage.
Debris flows and rockfalls are both important and
will be studied in the project. However, there is a range of debris
flows and they need
to decide which ones to model. The principal field areas
are Lecco and Seriana in the preAlps and Valcamonica in the Alps.
Giovanni presented
maps of the areas, including hazard maps. The initial database
for the work already exists. The hazard assessment GIS to be
produced will be
PC-based and will be portable between operating systems. It
will be based on data and maps available at the 1:10,000 scale but the
final product will
apply at the 1:25,000 scale. Application areas must be large
enough to provide a basis for statistical analysis, typically more
than 200 km2.
The discussion highlighted the need to understand the requirements
of the various project models, including data evaluation, and
the way in which
the models can be used in a GIS environment.
6.3
- WP3 UNIVERSITY OF PADOVA
Mario
Lenzi indicated that end-user interest in torrent control was the
reason for developing
the debris flow model. (The model specification should
therefore involve the end-users.) It will be quantitative but must
not be complex or
data-hungry. It will simulate the debris flow propagation
but not the triggering. It therefore needs a time-varying input
of water and sediment. The model will have two components : channel
routing for the
final reach of the main stream and fan deposition. Two basins
will be used for relevant data collection, of area 2.4 and 7 km2.
A form has
been devised to standardize data derived from different sources.
6.4
- WP4 UNIVERSITY OF NEWCASTLE UPON TYNE
James
Bathurst described the SHETRAN landslide sediment yield model and
its intended use.
The model is applicable at the catchment scale and is intended
to give the sediment yield arising from shallow landslides. The
Mario
nt size="2" color="#000080">model contains a number of simple rules
for determining
a)
the volume of material
in the landslide,
b) if landslides deposit their sediment at the site
of the failure or if they involve downslope transport in the form of
a debris flow, and
c) the runout distance of any debris flow. Information from
WP1 will help to check and refine these rules.
The
model will be used to simulate the impact of different land management
scenarios and climate scenarios on landslide occurrence and the
catchment sediment
yield, of importance for example to reservoir sedimentation.
Two catchments will be simulated, one in the Alps and one in
the Pyrenees: an early task is therefore to select suitable sites.
6.5
- WP5 UNIVERSITY OF NEWCASTLE UPON TYNE
Discussion
was limited to the web site, which is covered in Contractual
Matters.
7
- WORKPACKAGE LINKS
7.1
- WP1 INPUTS TO WP3 AND WP4
WP1
will provide data and process relationships which will improve the
WP3 and WP4 model
developments and applications. Inputs
to WP3 are:
-
detailed fan description (1-2 m resolution)
-
time-varying sedigraph as input to the debris flow model
-
grain size and geotechnical characteristics of debris flow
-
topography (eg longitudinal profile and channel cross sections of
the end reach
of the main stream).
The
Padova debris flow model should be applied at a site in the Pyrenees
towards the end
of the project (eg for the Zaragoza workshop). The Padova and
Zaragoza teams should therefore liaise over a suitable site.
WP4 requires that
the debris flow rules in the SHETRAN model should be checked
and refined as specified in Section 6.4. The Newcastle and Zaragoza
teams should liaise over the necessary work. While
WP1 is based mainly on the Pyrenees sites, data should also be
used from the two
Alpine areas as much as possible. The
partners developing or using models should circulate a list of the
model requirements,
including the desired quality of the data and how the data
should be collected. The partners collecting data should take these
requirements into
account.
7.2
- WP3 AND WP4 INPUTS TO WP2
This
link is central to the DAMOCLES project and provoked a long and
stimulating
discussion. The principal conclusions were:
a)
The WP2 regional GIS discretizes space using geomorphological units
(eg subcatchments
of varying size). It calibrates recorded channel debris flows
against largely time-independent parameters such as land-use and
geology to provide
a qualitative index for likelihood of debris flow occurrence
in each geomorphological unit. Application of the GIS provides
a spatially distributed
map of debris flow probability across the entire region.
The recorded debris flows may refer to different periods of time
or to a single
event. For example a map for the Leccho region was displayed
which is based on debris flows surveyed for a single event.m
Different models
can be developed for rockfalls, debris flows and landslides.
The recorded debris flows can also be presented in a separate
inventory map.
Because of its dependence on the use of recorded debris flow
data, the GIS model is essentially based on past or historic
conditions. If
land use or climate change in the future, the calibratedì functions
may no longer apply. The SHETRAN landslide model (WP4) cannot be
applied
at such large (regional scales) but it can help to enhance the GIS
model by providing
landslide scenarios for altered land use and climate conditions.
It can do this by providing landslide and debris flow distributions
for the possible future conditions: these distributions (and
any altered land
use conditions) are then the "virtual ground truth" which
form the input
for calibration of the GIS for the new conditions. As the GIS
model is being developed for the test areas near Milan, the SHETRAN
Alpine application
catchment should also be in this area, to allow maximum integration
of WP2 and WP4. The Newcastle and Milan teams should therefore
liaise over a
suitable site.
b)
The Zaragoza team are also producing a GIS model, but based on pixel
discretizations.
The two GIS techniques will be compared, probably for an area
in Lombardy.
c)
The Padova WP3 debris flow model can be used to investigate in detail
the hazard at
a site identified from the GIS analysis as requiring attention
(eg where it is planned to build a road or new infrastucture).
For this the GIS
analysis must indicate whether or not there is a debris flow
fan. The Padova model could then be used to study, for example, the
effect of check
dams for torrent control or to indicate if the fan is a hazard
area. The Padova model can be used for planning purposes, for a
quantitative evaluation
of sediment deposition on the fan (spatially distributed
and as a function of any construction), for studies where debris
flows have an economic implication.
d)
End-users at the regional scale may not be the same, or may not have
the same interests,
as those at the local scale. End-users believe in models
which fit their background knowledge, eg which simulate a landslide
at a site where
a landslide has been observed to occur. They may not be interested
in the underlying hydrology and other processes. It will be
important to stress
the model complementarity between WP2, WP3 and WP4 to the
relevant end-users.
e)
James, Giovanni and Mario will develop a flow chart which shows how
the various models
are linked and how they complement each other. In due course
this can go on the web site.
7.3
- WP1, WP2, WP3, WP4 INPUTS TO WP5
Discussion
was limited to the web site, which is covered in Contractual
Matters.
7.4
- INTEGRATION OF END-USERS INTO THE PROJECT
The
following points arose.
a)
Santiago Rios, speaking as an end-user, indicated that:
-
he needs to know the risk at the regional scale
-
he is interested in all the types of models in the project
-
the models need to be relatively simple to use
-
the end-users need to be integrated into the philosophy of the
project.
b)
The end-users should be involved from the beginning of the project
and should have
some task, such as providing data.
c)
End-users want a map or results, but not the details of how these
were obtained.
d)
End-users are driven by:
-
a need to solve a particular problem, or
-
legislation, eg they must provide a risk map at a certain scale.
e)
It is likely to be consultants who actually use the models, under
contract to the
end-users, rather than the end-users themselves. In the end-user
training courses it will therefore be as important to transfer
knowledge of how
to use the results as to give out the models. Possibly some
relevant consultants should be invited to the end-of-project
workshops and training
courses. Alternatively an outcome of the project could
be an annual short course, run for perhaps five years. (This could
be an important
component of the project Technology Implementation Plan.) (The
coordinator held meetings with the Italian end-users and their
project partners
immediately after the start-up meeting to ensure their full
integration.)
8
- CONTRACTUAL MATTERS
8.1
- WEB SITE
The
site will be used for internal (private project) and external
(public)
dissemination. The site will contain:
-
partner contact details, including links to partner web sites
-
end-user contact details
-
all project reports, including the contract document annex I and
appropriate publications
-
minutes of project meetings (after EC approval)
-
one-page description of each study area
-
one-page description of each model.
Material
for the site should be formally approved by the partners and
the coordinator.
The
site should be active after 6 months (by 31 August). Fausto Guzzetti
will circulate a
request for the necessary information in due course.
8.2
- EU CONTRACT/REQUIREMENTS
We
reviewed the contract. There were no outstanding problems but the
following points
were noted:
a)
Article 16. The Technology Implementation Plan must be delivered two
months after the
project end. We will discuss this at the next progress meeting.
b)
Article 18. A form of words acknowledging EC support but absolving
the EC of responsibility
for the web site content should be prepared for the
web site. Fausto Guzzetti will check the USGS web site for ideas.
c)
Partners should keep a detailed file of expenditure to support their
claims and to
help any audits by the EC.
d)
Subcontracts must be fully documented and checked.
8.3
- CONSORTIUM AGREEMENT
We
went through the draft Consortium Agreement which has been drawn up
by the University
of Newcastle. There was some discussion about the information
and software which will go into the public domain at the end
of the project.
Section 8.6 also states that defaulting partners will suffer
financial penalties. However, all partners need to read the Agreement
carefully and check it with their organizations. All partners
should send their
comments to the coordinator by the end of May.
8.4
- PAYMENTS
The
initial advance from the EC should be paid to the coordinator by the
end of April. The
coordinator should distribute the advance between the partners
by the end of May.
8.5
- TECHNOLOGY IMPLEMENTATION PLAN
This
will be discussed at the next progress meeting.
8.6
- QUALITY ASSURANCE
A
document on quality assurance procedures for hydrological instrumentation,
monitoring and data management is being prepared at the University
of Newcastle for a large field research programme. It should be
relevant to DAMOCLES
and copies will therefore be distributed to the partners
in due course. The purpose of the QA system is to ensure that the
project is planned
and executed in a clear and transparent way and that there
is a documented audit trail supporting all data produced during the
project.
We should adopt
a common approach to collection of new data, to ensure compatibility
between partners and to meet the needs of the models. For
existing datasets it should be specified how they were collected and
interpreted.
8.7
- PUBLICATIONS
There
must be a fair representation of relevant parties in the authorship
of papers arising from the project. For example, if a modelling
group wish to write
a paper describing simulations based on data collected by
another group, they should include a representative of the data
collection group
in the authorship. Similarly, assistant contractors, subcontractors
and end-users should be represented as appropriate.
Mario
eight: 100%; margin-top: 0; margin-bottom: 0" align="left">8.8
- REPORTING
a)
Meetings between partners should be recorded in a short report,
forwarded to the coordinator.
b)
Progress reports should be completed two weeks before each progress
meeting so that they can be circulated to all partners. These reports
can include discussion of work to date.
c)
The first 12-month report is due on 28 February 2001. The coordinator
may ask for draft copies at an earlier date to allow a summary of project
progress to be written.
d)
To enable partners to keep in touch with each other's progress between
meetings, they should distribute by email a short summary of their work
every two months. This summary can be in the form of a list of bullet
points. The first summaries are due on 2 June.
8.9
- NEXT MEETINGS
The
next progress meeting will be on 25-27 October in Zaragoza, beginning
at 9.30 on the 25th. There will be a field visit on the 27th.
Progress
reports are due on 13 October.
The
following meeting will be sometime in March-May 2001 at Newcastle.

|